Project duration: Approximately three (3) months
This project involves the installation of a new Schneider ISX solution that incorporates a 250kW frame Schneider UPS unit and eight (8) Schneider InRow Cooling units housed in a new hot isle containment system. The solution involved the installation of electrical feeders to support the UPS unit input and output power distribution as well as input feeders to the eight (8) InRow Cooling units and associated outdoor condenser units. Mechanical supply and return linesets were routed from the InRow Cooling units through the building and out to the exterior condenser units located in a mechanical courtyard. The project was closely coordinated with the owners and was completed on schedule.